Product · China–West axis · declared vs. observed

china_industrial_reality

A per-asset verdict, with evidence, on Chinese industrial buildout announced in Europe: what the company/press declared (capex, capacity, promised date — official source only) against what's documented as the real status today. Where an asset has a localizable site and a physical-measurement method has been validated on it, an independent measured delta is added — never mixed with documented claims without saying which is which. Not a company database (Rhodium/fDi already do that well), not an entity graph, not a monitoring platform — just the verdict per asset, with its source.

DOCUMENTED vs. MEASURED — never blurred. DOCUMENTED = what the company or press reported, with URL and date — never an NKO measurement. MEASURED = an independent physical delta from NKO's own LiDAR/satellite pipeline (the same measure_physical_change() already validated on 9 real landfill sites). Every project below is DOCUMENTED only, for now — see why in the next section.

Physical validation — two rounds, honest result

Round 1 (Zaragoza): tried the satellite method (Sentinel-1/2, no LiDAR) against the CATL–Stellantis gigafactory, first-stone 2025-11-26, with a success bar fixed before running. It failed — no sustained signal at the site, and the control zone drifted more than the site in one quarter, ruling out the site's isolated spikes as real. Full write-up: zaragoza_b05_conclusion.md.

Round 2 (4-site battery, pre-registered verdict rule): before declaring the method dead, we ran it against 3 more sites — Debrecen (CATL) and Szeged (BYD, the actual candidate assets), plus Tesla's Gigafactory Berlin-Brandenburg (Grünheide) purely as a method sanity check — alongside Intel's cancelled Magdeburg site as a negative control (construction never started there; the method must say so).

VALIDATED — the method works, on the right kind of site. Grünheide (real forest cleared for the gigafactory, 2020–2022) shows a clear, sustained signal in 2 of 3 methods (built-up index +2.95σ, vegetation index -2.99σ). Magdeburg shows no signal in any method, exactly as it should for a site where nothing was ever built. The method isn't broken and doesn't hallucinate.

But Debrecen and Szeged — the two candidate assets that would actually feed this product — still show no clear sustained signal, same as Zaragoza. The honest read: industrial construction on already-disturbed or agricultural land is a much smaller spectral/radar contrast than clearing a forest, and all three candidate sites still use a synthetic buffer polygon, not the real parcel — likely diluting whatever signal exists. Full matrix and numbers: b05_multisite_conclusion.md.

Consequence: the gate is no longer blocked on "maybe the method is broken" — it's proven capable. But no asset below has a real MEASURED result to publish yet, because none of the actual candidates has shown one. This page stays DOCUMENTED-only until a real parcel boundary is tried on Debrecen or Szeged.

Two more sensors tried, both closed honestly dead

Beyond the optical/SAR method above, two more free public sensors were tested as additional ways to detect real operation or buildout — both came back a clean negative, reported the same way as everything else on this page: pre-registered threshold, no reinterpreting after seeing the data.

B-06 (Landsat thermal) — DEAD. Tested surface-temperature anomaly across all 5 sites, including Grünheide as the same must-detect sanity check used above. It didn't: +1.01σ, half the +2.0σ threshold fixed before running — the pre-registration rule says that alone kills the method, no exceptions. Landsat's 100m thermal resolution likely mixes an isolated industrial building into surrounding-terrain noise. b06_thermal_conclusion.md.
B-09 (GHSL / WSF building footprints) — DEAD, before running. Checked the source documentation before spending any compute: GHSL's most recent real (non-projected) satellite epoch is 2018, and WSF is a single 2019 snapshot — both years before any of this batch's buildouts started (2022-2025). GHSL's own data package explicitly labels its 2025/2030 grids "Future grids projections", not measurements — using them here would have blurred DOCUMENTED with MEASURED. b09_ghsl_wsf_conclusion.md.

New MVP — regulatory/contract signal, blind-tested 5/5, now 13/13

Remote sensing (above) is dead on real candidate parcels for this asset class. A different method isn't: real, dated public signals — municipal/regional interest declarations, strategic-project status, public-consultation periods, resolved regulatory friction, and construction contracts — tracked per asset instead of per pixel. Before trusting it, it was blind-tested against 5 independent cases this method had not yet touched: for each one, a prediction was written and committed to source control before looking at current employment/municipal data, then compared honestly. Full write-ups: b11_alternative_signals_findings.md, b12_calb_sines_blind_result.md, b13_two_more_blind_result.md. With the method holding up 5/5, it was then applied directly (no longer blind) to the remaining 7 assets in the audit table below — all 13 are now covered.

Signal hierarchy, fixed before scoring any asset. 1) Primary — municipal/regulatory activity: the most reliable and the fastest to appear across all 5 blind cases. 2) Secondary confirmation — a construction contract with a date and a figure, but only if it's the contract for the factory building itself. A contract for polygon infrastructure (water, roads, utilities) is tracked separately and never raises the verdict — the one mistake made in this method's own blind prediction for Sunwoda Nyíregyháza, where a real, dated infrastructure contract was initially mistaken for progress on the factory (the same pattern showed up again extending to Gotion Šurany — a real €162M park-infrastructure tender, separate from the consortium's own €1.234B factory investment). 3) Tertiary, optional — employment. Weak or absent in early phases by construction of the phenomenon itself (there's nothing real to hire for yet), only sharp near production or with an explicit, dated hiring campaign. Fourth rule, added extending to Farasis and SVOLT: a regulatory milestone can be a cancellation (a city rescinding a contract) — that's a negative signal, not progress, and is kept out of the normal stage ladder entirely rather than mislabeled as "regulatory activity".

Now populated for all 13 catalog assets — 6 from the original blind tests, 7 from the direct extension:

AssetStageFactory construction contractEmployment
CATL DebrecenPRODUCTION_ACTIVE_OR_NEARnot confirmed (building itself already complete per press, but no named contractor+figure found)1,470 real employees today, 5th hiring round active
Envision AESC DouaiPRODUCTION_ACTIVE_OR_NEARSogea Caroni (VINCI Construction) + Equans France, started 2022-11active workforce, 950-contract target reached by end of 2024, up to 3,000 by 2029
Chery/EBRO BarcelonaPRODUCTION_ACTIVE_OR_NEARnot applicable — existing plant reconversion, no new-build contract~850 real employees today, EV production starting late-Nov-2026
Leapmotor/Stellantis FigueruelasPRODUCTION_ACTIVE_OR_NEARnot applicable — existing plant, no new-build contract~5,000 employees, 400 real hires already made for this line, 450-500 more posted
CALB SinesFACTORY_CONTRACTEDMota-Engil, €207.3M, 2026-05active postings (narrow, early-stage)
BYD SzegedPRE_PRODUCTION_ACTIVITYnot confirmed50+ active postings (Indeed, Sep-2026)
CATL–Stellantis ZaragozaPRE_PRODUCTION_ACTIVITYnot confirmedactive postings, JV/Stellantis attribution ambiguous
EVE Energy DebrecenPRE_PRODUCTION_ACTIVITYnot confirmed (structural works underway since Apr-2025)own careers portal live, Jan-2026 press cites a ~1,000-worker production start
Gotion InoBat ŠuranyREGULATORY_ACTIVEno — only a park-infrastructure tender found (MH Invest, €162M, 2024), explicitly excluded1,300 jobs declared, no active postings found
Sunwoda NyíregyházaREGULATORY_ACTIVEno — only a park-infrastructure contract found (KE VÍZ + Mészáros Zrt., 2024-02), explicitly excludeddeclared intent only, no active postings found
SAIC/MG FerrolREGULATORY_ACTIVEno — confirmed directly by source: permits due end-2026, construction 2027declared intent only (target job counts, not postings)
Farasis Bitterfeld-WolfenCANCELLED_KNOWN_OUTCOMEnever existed — construction never startednone — never materialized
SVOLT SaarlandCANCELLED_KNOWN_OUTCOMEnever existed — construction never startednone — never materialized

Code and the 12 automated checks (including the anti-conflation rule that a park-infrastructure contract can never register as a factory-building contract, and the rule that a cancellation is never scored as "regulatory activity"): regulatory_signal_state.py, test_regulatory_signal_state.py, mvp_regulatory_signal.md.

13 projects audited, real sources — not 20

We set out to audit 20 real Chinese industrial projects in Europe. 13 came back with a primary source we could verify live; the other 6 candidate names are known but not yet confirmed against an official source, so they're left out rather than filled in with weak data. Verdict counts as they actually came out: 3 CONVERTIBLE · 6 PARCIAL · 4 NO_CONVERTIBLE.

One structural finding along the way: Hungary has no free national LiDAR program (verified against the EU Joint Research Centre's JRC126223 report), which affects 4 of the highest-value projects here (CATL Debrecen, BYD Szeged, EVE Energy Debrecen, Sunwoda Nyíregyháza) — they'd depend on Sentinel alone, without a LiDAR baseline to anchor a volumetric delta.

ProjectDeclaredPromised / sourceDocumented statusVerdict
CATL–Stellantis Zaragoza (Contemporary Star Energy)
ES
€2.10B
50 GWh/año (LFP)
primera piedra 2025-11-26
merics.org · 2026-05
En construcción, en marcha (MERICS/Rhodium COFDI Update 2026, 2026-05)CONVERTIBLE
Gotion InoBat Batteries (JV Gotion/EnergyX 80/20), Šurany
SK
€1.23B
20 GWh/año (fase 1)
groundbreaking 2025-10-28
electrive.com · 2025-10
Producción de prueba 2026, plena 2027, en marcha (electrive.com, 2025-11)CONVERTIBLE
Envision AESC Douai (fase 1)
FR
€1.30B
9-10 GWh (fase 1)
propuesto 2023-10
nordfranceinvest.com · 2025-06
Ya operativo desde jun-2025 - construcción prácticamente terminada, poca señal física restante que medir (Yahoo Finance, 2025-06)CONVERTIBLE
CATL Debrecen (fase 1)
HU
€7.41B
40 GWh (fase 1)
licencia de producción 2026-08-25
merics.org · 2026
Retraso documentado real: incidente de exposición a níquel (9 empleados), orden de cese de trabajo 2026-08-25 en varios talleres; solicitud de licencia fase 2 RECHAZADA 2026-08-19 por error de etiquetado del plano (carnewschina.com, 2026-09-02)PARCIAL
BYD Szeged
HU
€4.21B
150.000 uds/año
producción en serie (reprogramada varias veces)
merics.org · 2026
Retraso documentado real, reprogramado varias veces (fin-2025→Q2-2026→producción en serie Q2/Q4-2026); producción de prueba iniciada feb-2026 (autopro.hu, digitimes.com, electrive.com, 2026-02)PARCIAL
EVE Energy Debrecen
HU
€1.35B
30 GWh (fase 1), suministra a BMW Neue Klasse
permiso de construcción 2025-03
fuelcellsworks.com · 2026-07
En plazo - obra estructural completada fin-2025, producción prevista 2027 (fuelcellsworks.com, 2026-07)PARCIAL
Sunwoda Nyíregyháza
HU
€1.55B
no verificado en esta pasada
anunciado 2023-07-27
merics.org · 2026
No verificado en esta pasada - solo cifra DECLARED confirmadaPARCIAL
CALB Sines
PT
€1.96B
no verificado en esta pasada
anunciado 2023-03-01
merics.org · 2026
No verificado en esta pasadaPARCIAL
SAIC/MG Ferrol, Galicia
ES
€200M
120.000 uds/año (fase 2)
apertura prevista 2028, anunciado 2026-06
automotiveworld.com · 2026-06
Fase de anuncio, sin construcción iniciada - oportunidad real de línea base ANTES de que empiece la obra (electrive.com, 2026-06)PARCIAL
Chery/EBRO Barcelona (Zona Franca)
ES
—
no especificado
producción iniciada 2024-11
chinadaily.com.cn · 2026-02
Retrasos documentados hasta 2026 por aranceles UE - fábrica EXISTENTE reconvertida, no obra nueva (detroitnews.com, 2026-02)NO_CONVERTIBLE
Leapmotor/Stellantis, Figueruelas
ES
—
40.000 uds/año inicial (B10)
producción desde 2026-08
electrive.com · 2026-03
Planta EXISTENTE de Stellantis, sin construcción nueva (electrive.com, 2026-03)NO_CONVERTIBLE
Farasis Bitterfeld-Wolfen
DE
€600M
6-10 GWh
anunciado 2019
electrive.com · 2022-05
CANCELADO - contrato de desarrollo urbano rescindido 2022-05, obra nunca empezó (electrive.com, 2022-05)NO_CONVERTIBLE
SVOLT Saarland (Überherrn + Heusweiler)
DE
€2.00B
24 GWh
anunciado 2024-10
electrive.com · 2024-10
CANCELADO completamente, salida de Europa confirmada 2025-01-31 (electrive.com, ministerio de Sarre, 2025-01)NO_CONVERTIBLE

CONVERTIBLE = localizable site + free baseline + Sentinel-observable, all three real. PARCIAL = missing one of the three (usually the LiDAR baseline, per the Hungary finding above). NO_CONVERTIBLE = either the project was cancelled before any construction, or it's a conversion of an already-existing plant with no new physical footprint to measure (Chery/EBRO Barcelona, Leapmotor/Stellantis Figueruelas).

Each of these 13 also has its own page with a downloadable machine-readable record: see all audited assets →