DOCUMENTED only — no MEASURED result yet for this asset

Envision AESC Douai (fase 1)

Real polygon + LiDAR/Sentinel-free country - measurable once B-05 asset-level gate opens

FieldValue
CountryFR
Declared capex€1,300,000,000
Declared capacity9-10 GWh (fase 1)
Declared datepropuesto 2023-10
Declared sourcehttps://nordfranceinvest.com; Yahoo Finance (jun-2025) (2025-06)
Documented status (press)Ya operativo desde jun-2025 - construcción prácticamente terminada, poca señal física restante que medir
Documented sourceYahoo Finance (2025-06)
Measurability verdictCONVERTIBLE

Regulatory/contract signal (new MVP, blind-tested 5/5 across independent cases — a different method than the satellite one above):

FieldValue
StagePRODUCTION_ACTIVE_OR_NEAR — Real, current workforce at the site (production active or imminent)
Regulatory/municipal milestones found3
Factory-building construction contractYES — Sogea Caroni (filial de VINCI Construction), en consorcio con Equans France y Lucas & Gaillard Architectes, 2022-11
Infrastructure contract (park/utilities — never counted as factory progress)not found/not applicable
Employment signalactive_workforce — Fabrica ya operativa (confirmado en el catalogo, jun-2025). Contratacion real y sustancial: objetivo de 950 contratos permanentes a fin de 2…

Source of this research round: catalog-extension-2026-09-06. Full method and its 5/5 blind-test result: china_industrial_reality — regulatory signal MVP.

Machine-readable record (same fields as this page):

envision-aesc-douai.json

DOCUMENTED = declared by the company/press, never measured by NKO. MEASURED = NKO's own physical measurement (LiDAR/Sentinel). Never mixed without marking which is which. Method status: china_industrial_reality product page.