DOCUMENTED only — no MEASURED result yet for this asset

CATL Debrecen (fase 1)

Partially measurable - some real constraint on polygon/coverage/country access

FieldValue
CountryHU
Declared capex€7,405,000,000
Declared capacity40 GWh (fase 1)
Declared datelicencia de producción 2026-08-25
Declared sourcehttps://merics.org (COFDI 2026) (2026)
Documented status (press)Retraso documentado real: incidente de exposición a níquel (9 empleados), orden de cese de trabajo 2026-08-25 en varios talleres; solicitud de licencia fase 2 RECHAZADA 2026-08-19 por error de etiquetado del plano
Documented sourcecarnewschina.com (2026-09-02)
Measurability verdictPARCIAL

Regulatory/contract signal (new MVP, blind-tested 5/5 across independent cases — a different method than the satellite one above):

FieldValue
StagePRODUCTION_ACTIVE_OR_NEAR — Real, current workforce at the site (production active or imminent)
Regulatory/municipal milestones found2
Factory-building construction contractnot found/confirmed
Infrastructure contract (park/utilities — never counted as factory progress)not found/not applicable
Employment signalactive_workforce — 1.470 empleados reales hoy, objetivo 2.300 a fin de ano, 5a campana de contratacion activa (jul-sep 2026).

Source of this research round: B-11. Full method and its 5/5 blind-test result: china_industrial_reality — regulatory signal MVP.

Machine-readable record (same fields as this page):

catl-debrecen-f1.json

DOCUMENTED = declared by the company/press, never measured by NKO. MEASURED = NKO's own physical measurement (LiDAR/Sentinel). Never mixed without marking which is which. Method status: china_industrial_reality product page.